December 5, 2014  ·  1 min read  ·  Materials

Hampton Inn & Suites 107-Key FF&E Procurement Matrix & Color Board Archive: Smith County, TX

Organizing 258 specification cut sheets, color boards, and a 107-key eight-room-type FF&E procurement workbook for a Hampton Inn & Suites in Smith County, TX.

Hampton Inn & Suites 107-Key FF&E Procurement Matrix & Color Board Archive: Smith County, TX

A 100-plus key hotel FF&E buyout slows down quickly when design palettes, vendor cut sheets, and room-mix quantities are reviewed in silos. On a 107-key Hampton Inn & Suites project in Smith County, TX, the procurement team aligned the conceptual finish boards, Hilton's 258-page specification manual, and every itemized takeoff schedule into one traceable purchasing matrix.

How the 107-key buyout stayed aligned

  • Color boards and interior elevations: A 13-page presentation package tied approved finish palettes directly to rendered views for the lobby, breakfast zone, community table, and guestroom carpet layout.
  • Full specification and cut-sheet indexing: Public space (P100 through P600) and guestroom (G100 through G600) cut sheets were matched against the 258-page spec book across casegoods, seating, mattresses, drapery, lighting, carpet, mirrors, back of house, restrooms, recreation, and pantry graphics.
  • Eight-configuration unit takeoff: Quantities were rolled up across all 107 keys, covering 12 King rooms, 18 King Sofa rooms, 28 King Studios, 30 Queen/Queen rooms, 3 ADA King rooms, 4 ADA King Sofa rooms, 4 ADA King Studios, and 8 ADA Queen/Queen units so fabric yardage, lamp counts, and vanity sizes stayed exact.

Indexing every item back to Hilton spec codes (G101 through G633 and P101 through P633) gave ownership clear cost accountability from design review straight through factory purchase orders.

More in Materials

Related field notes & case studies

More real numbers, takeoffs, and post-mortems from the operation. View all entries →